Ramsdell Water Main Project

Updated 2/28/2018

Under Construction Sign

The Ramsdell Water Main Project is going to construction. Pape & Sons Construction was awarded the contract for this project. The contracts are signed and a pre-construction meeting is being held March 2, 2018. The Contractor’s schedule provides for construction to start the week of March 5th. Construction will begin at Ramsdell and Contra Costa and work their way west along Ramsdell. It is anticipated to take until Mid-April to complete the project. During this time, we ask for your patience during this construction and please use an alternate route if possible and avoid Ramsdell. Residents along Ramsdell from Contra Costa to San Juan will have access during construction. On street parking along this route of Ramsdell will be limited during construction. Thanks again for your patience during this construction period. If you have any questions feel free to contact Public Works 253-564-8900.