Update 5/31/2023
Our 5th and final structure will be installed tomorrow Thursday June 1, 2023.
Once this final structure is installed Pape & Sons will be able to do the final asphalt repairs to complete this project.
We thank you for your continued patience, support, and understanding as we work with Pape & Sons to successfully complete this stormwater upgrade project.
Please reach out to Public Works between the hours of 7:30am to 3:00pm Monday through Friday If you have any questions or concerns .
Sincerely:
City of Fircrest Public Works Department
(253) 564-8900
publicworks@cityoffircrest.net
Update 5/25/2023
The City of Fircrest Public Works Department along with Pape & Sons Construction Inc., continue to replace catch basins with filtered type structures on Estate Place and Emerson St. There has been a delay in this project due to material delivery and is taking longer than the expected 2-week duration.
We are expecting the final structure to be, tentatively, delivered next week. Once this final structure is installed Pape & Sons will be able to do the final asphalt repairs to complete this project.
We thank you for your continued patience, support, and understanding as we work with Pape & Sons to successfully complete this stormwater upgrade project.
Please reach out to Public Works between the hours of 7:30am to 3:00pm Monday through Friday If you have any questions or concerns .
Sincerely:
City of Fircrest Public Works Department
(253) 564-8900
publicworks@cityoffircrest.net